Brineworks' EIC Accelerator Pulls CO2 From Air With Saltwater
Aviation and shipping cannot realistically be electrified, so they need synthetic fuels that are chemically identical to the fossil ones. Those fuels need two cheap feedstocks, CO2 and hydrogen, and both are currently too expensive. Brineworks, based at Amsterdam Science Park, runs a hybrid electrolysis system on saltwater that captures CO2 from the air and produces green hydrogen as a co-product, which the CORDIS summary of its EIC project says cuts overall process costs by up to 50%.
The EIC Accelerator selected the project at its October 2024 cut-off for blended finance, and CORDIS records a grant of €1,827,831.29 from February 2025 to January 2027, one of the smaller awards in the cut-off. The project claims a levelised cost of CO2 extraction as low as €68 per tonne against €500 to €600 for incumbent direct air capture. In June 2026 the company opened a demonstration plant, and in September it sold its first carbon removal.
Company file
- Legal entity
- Brineworks B.V., Science Park, Amsterdam
- CEO
- Gudfinnur Sveinsson, co-founder
- Investors
- SeaX Ventures (2025 lead), Pale Blue Dot (2024 lead), First Momentum, AiiM Partners, Energie360°, Katapult
- Technology
- Saltwater-based electrolyser capturing CO2 and co-producing hydrogen, run intermittently on renewable power
- Target applications
- E-fuels including e-SAF, e-methanol and e-natural gas, plus cement, plastics and carbon removal
- First plant
- Demonstration plant at Amsterdam Science Park, opened June 2026
- EIC project
- BRINEWORKS, agreement 101218440, February 2025 to January 2027
From ocean capture to air capture
The company's framing has shifted. When Pale Blue Dot led a round of about €2 million in September 2024, Brineworks described its approach as direct ocean capture: seawater electrolysis extracting CO2 and hydrogen from the ocean, with CEO Gudfinnur Sveinsson calling it "sustainable, scalable, and cost-effective", as Carbon Herald reported. Today the website leads with "ultra low-cost Direct Air Capture", and the CORDIS summary describes capturing CO2 from air using saltwater. The company's description of what it does has changed from ocean capture to air capture.
In September 2025 a second round of €6.8 million was led by SeaX Ventures with Pale Blue Dot, First Momentum, AiiM Partners, Energie360° and Katapult, bringing disclosed equity to about €8.8 million alongside the EIC grant.
The record
From ocean capture to a demonstration plant in Amsterdam
Brineworks' electrolyser pulls CO2 out of the air using saltwater and produces green hydrogen at the same time.
- Sep 2024First roundLed by Pale Blue Dot, for technical development and a first pilot€2M
- Oct 2024EIC Accelerator cut-offSelected for blended finance under the open call
- Feb 2025EIC project startsTwo years to take the hybrid electrolyser toward commercial use€1.83M
- Sep 2025Second roundLed by SeaX Ventures with Pale Blue Dot, First Momentum, AiiM Partners, Energie360° and Katapult€6.8M
- Jun 2026Demonstration plant opensAmsterdam Science Park plant designed to capture up to 100 tonnes of CO2 a year
- Sep 2026First carbon removal salePre-purchase of 500 tonnes through Milkywire, backed by Salesforce
- Jan 2027EIC project endsScheduled end of the EIC projectScheduled
CORDIS; Brineworks updates; Carbon Herald, September 2024; tech.eu.
The demonstration plant and the first sale
In June 2026 Brineworks opened its demonstration plant at Amsterdam Science Park, designed to capture up to 100 tonnes of CO2 a year while co-producing green hydrogen, powered by renewable electricity. The company said early data supported its target of capturing CO2 below €100 per tonne at scale, and described the plant as validating system performance ahead of a first commercial plant. It did not publish the data.
In September 2026 it secured a pre-purchase of 500 tonnes of durable carbon removal through Milkywire, backed by Salesforce, as one of eight suppliers in that purchasing round, part of Salesforce's commitment to contract $100 million of durable carbon removal by 2030. That is a real customer, though the amount paid was not disclosed.
The cost claim
€68 a tonne against €500 to €600 for incumbent capture
The low figure is the levelised cost the EIC project says the technology could reach; the high figures are what the project and the company give for today's direct air capture. None has been independently verified.
CORDIS project summary; Brineworks website, October 2026. Values in € per tonne of CO2.
The plan
An electrolyser that delivers CO2 and hydrogen on site for e-fuel producers at as little as €68 per tonne of CO2, sold through plant licences, equipment, maintenance and royalties.
The record so far
A 100 tonne-a-year demonstration plant running, a 500 tonne carbon removal pre-purchase and €8.8M of equity; no published performance data, no commercial plant and no e-fuel customer.
- Working electrolyser at demonstration scaleBuiltAmsterdam plant opened June 2026.
- First paying carbon removal buyerSigned500 tonnes via Milkywire, September 2026.
- Cost below €100 per tonneClaimedCompany says early data supports it; data not published.
- Commercial plant and e-fuel customersIn discussionCompany says it is talking to e-fuel and carbon removal partners.
A small grant for a hardware company
At €1.83 million, the EIC grant is below the €2.5 million most beneficiaries in this cut-off received, and it is smaller than either of the company's private rounds. The award was blended finance and no EIC Fund equity has been announced. The business model the project describes is broad for a company this size: selling CO2 and hydrogen from the demonstration plant, licensing the plant design, selling electrolysers, spare parts and maintenance, and taking royalties on customers' output.
Funding
€8.8M of equity and a €1.83M grant
The EIC award was blended finance; no EIC Fund equity investment has been announced.
Brineworks and investor announcements, September 2024 and September 2025; CORDIS. Values in € millions.
Cheap CO2 is the bottleneck in European e-fuel rules
The EU is requiring aviation fuel to contain a rising share of synthetic fuel, and those fuels need CO2 that does not come from fossil sources. That is the policy logic behind the grant: if capture costs stay at several hundred euros a tonne, e-SAF stays unaffordable. Brineworks' claim to matter is not the capture alone but the pairing, hydrogen and CO2 from one machine at one site, which would let fuel plants be built near renewable power rather than near a CO2 source.
Verdict
Brineworks has done more in 20 months than most companies in this cut-off: a demonstration plant running, a first carbon removal buyer, and €8.8 million of private money behind a €1.83 million grant. The number everything depends on, the cost per tonne, is still only a company claim, and the plant that would test it at scale has not been built. The open question is whether the early data it says supports €100 a tonne will be published.
Sources
- CORDIS, BRINEWORKS project fact sheet
- Brineworks, demonstration plant opens in Amsterdam, June 2026
- Brineworks, Salesforce-backed carbon removal purchase through Milkywire, September 2026
- Brineworks, technology and applications
- Carbon Herald, Brineworks secures $2M for direct ocean capture, 19 September 2024
- tech.eu, Brineworks secures $2.2M, 12 September 2024
Industry
Climate and environmentCarbon management
- Focus
- Direct air capture
- Technologies
- Electrochemistry
- Electrolysis
- Keywords
- E-fuels
- Sustainable aviation fuel
- Hydrogen
- Carbon removal