C2CA's EIC Accelerator Turns Old Concrete Back Into Cement

21 October 20261,102 words6 min

Cement accounts for about 8% of global CO2 emissions, and the world throws away some 3 billion tonnes of concrete a year. Most of it is crushed into low-grade aggregate, and the cement paste in it, the part that was once the binder, is treated as waste. C2CA Technology, a spin-out of TU Delft now trading as everox, recovers that paste and reactivates it into a supplementary cementitious material it calls Activated Cement Paste, which it says can replace up to 30% of the cement in a new concrete mix.

The EIC Accelerator selected the project at its October 2024 cut-off for blended finance, and CORDIS records a grant of €2,499,999 from June 2025 to May 2027 to complete the flagship plant, demonstrate the technology at industrial scale and build a smaller testing facility with a materials laboratory. By 2024 the company had built its core machines at industrial scale and processed more than 1,000 tonnes of waste concrete.

€2.5MEIC Accelerator grant for the C2CA project
100,000 tAnnual permitted capacity of the first commercial plant
30%Of cement that Activated Cement Paste can replace

Company file

Legal entity
C2CA Technology BV, Keileweg 80, Rotterdam; trading as everox since July 2025
Origin
Spin-out of TU Delft
CEO
Thomas Petithuguenin, appointed 2022
Investors
Chrysalix Venture Capital, InnovationQuarter's Energy Transition Fund Rotterdam, Titan Cement, Taaleri Bioindustry
Outputs
Activated Cement Paste, recycled coarse and fine aggregates, fine inert filler
Partners
Dura Vermeer (joint venture on the plant), Rudus in Finland, Mota-Engil in Portugal, RALMAX, ReThink
EIC project
C2CA, agreement 101217884, June 2025 to May 2027

Recovering everything, not just the gravel

The company's argument against the recycling industry it competes with is that crushing concrete into aggregate destroys the valuable part. Its process recovers all fractions, with indicative yields of about 60% recycled coarse aggregate, 20% Activated Cement Paste, 15% recycled fine aggregate and 5% fine inert filler. The paste is the point: it is a substitute for fly ash and slag, the traditional cement extenders that are disappearing as coal plants and blast furnaces close. The project also argues against the alternatives, calcined clay and mine tailings, as costly or energy-intensive to make and move.

Because the plant is small, low-energy and needs little space, the company says it can sit near cities where both the waste and the demand are, which cuts transport. It joined the EU-funded CITADEL project to electrify its process and the DETOCS project on concrete sustainability data.

What comes out

Four materials from one waste stream

Indicative yields from the company; the share depends on the input concrete. Activated Cement Paste is the valuable fraction, able to replace up to 30% of cement in a new mix.

everox technology page, October 2026. Percent of output.

The flagship, and what is not finished

On 10 September 2026 the company held its first Open Days at the site of its first commercial-scale plant in the Netherlands, built with joint venture partner Dura Vermeer, and reported that construction was advancing and the facility is permitted to process 100,000 tonnes of demolition concrete a year. Visitors saw pilot plant demonstrations and the flagship site. Since 2022 the pilot has processed several thousand tonnes.

The gap is certification. The company says its four materials are "advancing through EU-standard recognition and national approval processes in the Netherlands" and that it is pursuing a European Technical Assessment for CE marking across the EU. Until that is granted, the materials cannot be sold freely across Europe. CORDIS shows no periodic report for the project.

The record

From a TU Delft spin-out to a plant under construction

The company, formerly C2CA Technology, rebranded as everox in July 2025; the legal entity is still C2CA Technology BV.

  1. 2022Pilot plant and new CEOPilot facility starts operating; seed round announced with Thomas Petithuguenin as CEO
  2. Sep 2024Series ALed by impact investors and strategic partners including InnovationQuarter's Energy Transition Fund Rotterdam and Titan Cement€10M
  3. Nov 2024Taaleri Bioindustry investsFinancing for a full-scale commercial plant in Rotterdam
  4. Jun 2025EIC project startsTwo years to finish the flagship plant and build a testing facility with a materials lab€2.5M
  5. Jul 2025Rebrand to everoxC2CA Technology BV announces the new name
  6. Sep 2026First Open Days at the flagshipConstruction advancing on the commercial plant, built with joint venture partner Dura Vermeer
  7. May 2027EIC project endsScheduled end of the EIC project; a Series B is planned for early 2027Scheduled

CORDIS; everox news archive; Taaleri; Silicon Canals.

The plan

A finished flagship plant proving the process at industrial scale, a testing facility with a materials lab, and a cement substitute sold across Europe.

The record so far

A pilot that has processed several thousand tonnes, a commercial plant under construction with a major contractor, memoranda of understanding in Finland and Portugal; no completed plant, no certification, no sales figures.

  1. Industrial-scale machinesBuiltCore machines built and over 1,000 tonnes processed by 2024, per CORDIS.
  2. Flagship commercial plantUnder constructionShowcased in September 2026; not operating.
  3. Material certificationIn progressEU standard recognition and a European Technical Assessment still being pursued.
  4. Commercial salesNot reportedPartnerships are memoranda of understanding; no volumes or revenue public.

Equity, a grant, and a Series B planned

The company raised a €10 million Series A in September 2024 from impact investors and strategic partners including InnovationQuarter's Energy Transition Fund Rotterdam and Titan Cement, after an earlier seed round from Chrysalix Venture Capital that also brought in the current CEO. In November 2024 Taaleri Bioindustry invested to enable the Rotterdam plant, which it described as processing about 150,000 tonnes a year, a larger figure than the 100,000 tonnes the company's own 2026 statement gives as the permitted capacity.

The company announced the EIC award in August 2025 as €12.5 million of EIC Accelerator funding, which implies the €2.5 million grant plus €10 million of conditional equity; no EIC Fund investment has been announced. In September 2026 it said it was working with partners and investors toward a Series B in early 2027, citing €10 million of Series A money and the €2.5 million grant as what it has secured so far.

Funding

€10M of equity and a €2.5M EU grant

The company announced the EIC award as €12.5M in total, meaning a €2.5M grant plus €10M of conditional equity; no EIC Fund investment has been announced. Taaleri Bioindustry's investment for the Rotterdam plant was not quantified publicly.

everox news, August 2025 and September 2026; CORDIS. Values in € millions.

A European answer to vanishing fly ash

Europe's cement industry has a specific problem the EIC is funding against: the cheap supplementary materials that reduce clinker in cement, fly ash from coal power and slag from steel, are going away as those industries change, while CO2 rules tighten. A substitute made from demolition waste in the same city is attractive on emissions and on supply security, which is the argument everox makes about dependence on global supply chains. Its expansion plan names the UK, North America, the Middle East and Asia after Europe.

Verdict

This is a company doing the hard, slow part: a plant under construction with a major Dutch contractor, a pilot with years of data, and an industrial partner list that reads like a cement conference. The two things that would make it real are still pending: the finished plant, and certification of its materials. Completing the flagship plant is part of the EIC project, which ends in May 2027; no date for certification is public.

Industry

Climate and environmentRecycling

Focus
  • Resource recovery
Technologies
  • Materials processing
  • Mineral processing
Keywords
  • Construction materials
  • Cement
  • Circular economy
  • Industrial decarbonisation