Co-reactive Puts EIC Accelerator Money on Carbon-Storing Cement
Cement makers have long cut the carbon in their product by mixing in waste from two other industries: fly ash from coal power stations and granulated slag from blast furnaces. Both supplies are shrinking as those plants close or convert. Co-reactive, a 2024 spin-off of RWTH Aachen, wants to replace them with a powder made by reacting captured CO2 with ground silicate rock or steel slag. The company says each tonne of the result stores about 330 kilograms of CO2.
The EIC Accelerator selected Co-reactive at its 1 October 2025 cut-off for blended finance, and CORDIS files the project under the EIC Challenge on the acceleration of advanced materials development and upscaling. CORDIS records grant agreement 101297983, CO-REACTIVE, with an EU contribution of €2,241,879 from 1 June 2026 to 31 May 2028. CORDIS gives no figure for the total project cost, and no EIC equity amount has been published.
Company file
- Legal entity
- Co-reactive GmbH, Amtsgericht Wuppertal HRB 36552 (formerly Amtsgericht Düsseldorf HRB 104000)
- Founded
- Articles of association dated 26 January 2024, based on doctoral research by Andreas Bremen at RWTH Aachen
- Seat
- Ludenberger Strasse 44, Erkrath, near Düsseldorf, since early 2026
- Managing directors
- Andreas Bremen (CEO), Orlando Kleineberg (CTO), Willi Peter (CCO)
- Share capital
- €37,203, after an increase of €12,203 registered in November 2025
- Investors
- HTGF (lead), NRW.Bank, HBG Ventures, AFI Ventures, Evercurious VC, business angels
- Public support
- EXIST research transfer, seven-figure BMWE grants, EIC Accelerator
- EIC project
- CO-REACTIVE, agreement 101297983, June 2026 to May 2028
- Staff
- Not published
Cement is running out of its cheapest substitutes
The project summary in CORDIS sets out the case: cement causes 8% of global CO2 emissions, each tonne of Ordinary Portland Cement releases about 850 kilograms of CO2, and the supplementary cementitious materials the industry uses to replace part of the clinker are "now in short supply due to the phase-out of coal-fired power plants and the decarbonization of steelmaking." Anna Stetter, an investment manager at HTGF, said when the seed round was announced that fly ash prices had in some cases quadrupled over two years, according to HTGF and Trending Topics.
Regulation adds pressure from the other side. The project names the EU emissions trading system and the carbon border adjustment mechanism, which the European Commission applies to cement, among other sectors, in its definitive regime from 1 January 2026. The project argues that these rules are "driving up the cost of carbon compliance", and presents its material as an answer to both pressures at once: a substitute that does not depend on coal or blast furnaces, made from slag that European steelmakers already produce.
The carbon claim
850 kg of CO2 per tonne of cement against a claimed 330 kg stored
CORDIS gives about 850 kg of CO2 emitted per tonne of Ordinary Portland Cement and says each tonne of the company's material stores 330 kg. Regional press reported up to 300 kg. Neither figure has been independently verified.
CORDIS, CO-REACTIVE objective; Radio Neandertal, 28 April 2026. Kilograms of CO2 per tonne of material.
How the process works
The company's website and an nbau report of July 2025 describe the same chain. Magnesium or calcium silicates, such as olivine, or slags from metallurgy are milled, mixed with water and fed with CO2 into a tubular reactor at high pressure and temperature. The CO2 ends up bound as carbonates alongside amorphous silica, which reacts in cement as a pozzolan. A filter press and a rotary dryer turn the slurry into a fine powder the company calls CO-SCM. The CO2 can come from cement works, waste incinerators, biogas plants or direct air capture, and the plant can sit next to the source.
CORDIS calls the reactor "the world's first TUBULAR CO-Reactor for CO2 mineralization", which is the company's own description in its application. The difference from the established substitutes is where they come from: fly ash and granulated slag are by-products whose supply depends on power stations and blast furnaces, while CO-SCM is made on purpose, in what the HTGF release describes as a continuous process designed as a drop-in for existing cement production lines.
Co-reactive is not alone with the idea. Holcim says it has used Paebbl's mineralised CO2 powder, Rebond, in a concrete slab for the foundations of a logistics centre in southern Germany, with 15% less cement than the reference mix. Co-reactive took part in the 2024 cohort of the same group's Holcim MAQER Ventures accelerator; the accelerator's page does not say that it placed or won anything, and no supply agreement between the two has been announced.
The figures are the company's own
The performance numbers in public all come from the company or from articles based on its information. The nbau report gives a strength activity index of 99 to 106% at 25% replacement of CEM I, comparable with blast furnace slag. The Carbon Drawdown Initiative, which backs the company, wrote in July 2025 that mortars with 25% CO-SCM matched the strength of pure Portland cement in pilot tests and that the process converts up to 95% of the CO2. No test report, certificate or independent laboratory result could be found in a search on 4 November 2026.
The storage figure also varies by source. CORDIS and the company's site give 330 kilograms of CO2 per tonne; Radio Neandertal reported "up to 300 kg" when the plant opened; nbau quoted 330 kilograms and, for olivine-based material, up to 500 kilograms. CORDIS adds that three tonnes of CO-SCM are made "for every ton of CO2 avoided", which matches the 330-kilogram figure: three tonnes at 330 kilograms each bind about one tonne.
What the company says
A carbon-negative cement substitute storing about 330 kg of CO2 per tonne, priced competitively with conventional SCMs, as strong as Portland cement at 25% replacement, and a drop-in for existing plants.
What the record shows
A demonstration plant opened by a state minister, a funded EU project and a €6.5M seed round. No independent test data, no price, no product certification and no named buyer of the material were found.
From pilot reactor to demonstration plant
The Carbon Drawdown Initiative put the pilot reactor at 10 tonnes a year in July 2025. In January 2026, HTGF and Trending Topics reported that the company would expand to a continuous demonstration plant of about 1,000 tonnes a year by the second quarter of 2026, followed from 2027 by first-of-a-kind plants with industrial partners, which neither names.
The demonstration plant step happened on time. North Rhine-Westphalia's economy minister Mona Neubaur opened it in Erkrath on 27 April 2026, with the chief executive of NRW.Bank, Gabriela Pantring, attending, according to Mittelstandsmagazin NRW; Radio Neandertal reported the opening on 28 April with a planned output of about 1,000 tonnes a year. The company's own news page dates its item on the opening 7 July 2026. Neither article gives the investment cost, staff numbers or the plant's output so far, and Mittelstandsmagazin noted that the company gives no exact details of its chemical process.
The scale-up
From 10 tonnes a year to a target of 300,000
Annual output at each step as the company and its investors describe it. Only the pilot and the demonstration plant are said to exist; the first-of-a-kind and industrial plants are plans.
Carbon Drawdown Initiative, 10 July 2025 (pilot reactor); HTGF, 28 January 2026 (demonstration plant and plans); Radio Neandertal, 28 April 2026. Tonnes per year.
Co-reactive also says it has joined GeoCRM, a research project funded by the EU's regional and Just Transition funds with thyssenkrupp MillServices & Systems, the VDEh-Betriebsforschungsinstitut, the FEhS building materials institute and RWTH Aachen. The project aims to recover critical raw materials from steel slag and carbonate what remains; its budget is not stated on the company's page.
A young company that has moved fast
The register records a string of changes in two years. The articles of association are dated 26 January 2024, and Bremen and Kleineberg were entered as managing directors on 27 March 2024, according to register data republished by webvalid. On 10 October 2025, nine days after the EIC cut-off, the shareholders resolved to raise the share capital by €12,203 to €37,203 and to move the seat from Düsseldorf to Erkrath. The Wuppertal register took the company over as HRB 36552 on 12 February 2026, with Willi Peter as a third managing director. No insolvency notice appears in either record, and no filed accounts with revenue, equity or staff figures could be read for this article.
The research base is documented. RWTH Aachen announced on 2 February 2024 that Co-Reactive, from its Aachener Verfahrenstechnik institute, was one of three winners of the 2023 Innovation Award, quoting Bremen: "As a result of our research, we can now store CO2 as a mineral solid." The team was funded through EXIST research transfer, a programme of the federal economy ministry, and nbau reports that it won the start-up category of the DGNB Sustainability Challenge 2025.
The money
A €6.5 million seed round, then a €2.24 million EU grant
Two separate figures from two separate documents, not a total. The BMWE grants are described only as seven-figure, and no EIC Fund equity amount has been published.
HTGF, 28 January 2026; CORDIS, grant agreement 101297983. € millions.
What the EIC project has to show by 2028
The EIC announced on 17 February 2026 that it had selected 61 companies out of 121 interviewed for proposed support of €467 million, per the ATHENA grant office's republication of the EIC's notice. Co-reactive's own announcement does not state its grant or equity amounts. The project started in June 2026, so CORDIS shows no report or deliverable yet, which is normal at this stage.
- Continuous tubular reactor at demonstration scalePlant openedOpened 27 April 2026 per Mittelstandsmagazin NRW; no output figures published.
- Material storing 330 kg of CO2 per tonneCompany claimSources give 300, 330 and up to 500 kg; no independent measurement found.
- Cement performance at 25% replacementCompany dataStrength index of 99 to 106% per nbau; no published test report.
- Industrial plants with partners from 2027Not yet duePartners unnamed; no customer or offtake agreement announced.
The record
From an Aachen laboratory to an Erkrath demonstration plant in about two years
Co-reactive's dates from the register, its investors, the EIC and regional press. The EIC project has not reached its first reporting period.
- Jan 2024Company foundedArticles of association dated 26 January 2024, Düsseldorf register HRB 104000, share capital €25,000
- Feb 2024RWTH Innovation AwardCo-Reactive of the Aachener Verfahrenstechnik institute named among three winners of the 2023 award
- Jul 2025DGNB Sustainability ChallengeWinner of the start-up category, with a pilot plant then planned for 2026
- Oct 2025EIC Accelerator cut-offApplication to the 1 October 2025 cut-off; shareholders resolve a capital increase to €37,203 and a move to ErkrathBlended finance
- Jan 2026Seed roundLed by HTGF with NRW.Bank, HBG Ventures, AFI Ventures, Evercurious VC and angels, plus seven-figure BMWE funding€6.5M
- Feb 2026EIC selection and new seatOne of 61 companies selected by the EIC; registered in Wuppertal as HRB 36552 after the seat move
- Apr 2026Demonstration plant opensOpened in Erkrath on 27 April by NRW economy minister Mona Neubaur, about 1,000 tonnes a year
- Jun 2026CO-REACTIVE startsGrant agreement 101297983 for the tubular CO2 reactor€2.24M
- May 2028CO-REACTIVE endsScheduled end of the EIC projectScheduled
RWTH Aachen, 2 February 2024; register entries via online-handelsregister.de and webvalid.de; nbau, 31 July 2025; HTGF, 28 January 2026; EIC via ATHENA, 17 February 2026; Mittelstandsmagazin NRW, 2 May 2026; CORDIS.
Verdict
Co-reactive is working on a real gap: the cement industry's traditional clinker substitutes are in short supply as coal power is phased out and steelmaking decarbonises, as the project sets out. In two years the company has gone from a university prize to a demonstration plant that opened within the quarter its investors had announced. What it has not shown in public is the evidence a cement buyer would ask for: independent strength and durability tests, a verified CO2 balance, a price and a first customer. The EIC project runs to May 2028, and the first-of-a-kind plant planned from 2027 will be the test.
The reporting is based on publicly available sources, listed below.
Sources
- CORDIS, CO-REACTIVE project fact sheet, grant agreement 101297983
- Co-reactive, company website
- Co-reactive, selected for the EIC Accelerator
- Co-reactive, GeoCRM research project
- HTGF, Co-reactive secures €6.5 million in seed funding, 28 January 2026
- Trending Topics, Co-reactive secures €6.5 million, 28 January 2026
- Mittelstandsmagazin NRW, Erkrather Start-up Co-reactive: Zementersatz mit Ministerbesuch, 2 May 2026
- Radio Neandertal, Co-reactive eröffnet Anlage in Erkrath, 28 April 2026
- nbau, Co-reactive: CO2-Mineralisierungstechnologie für klimapositive Baustoffe, 31 July 2025
- Carbon Drawdown Initiative, Portfolio spotlight: Co-reactive, 10 July 2025
- Online-Handelsregister, Co-reactive GmbH, Amtsgericht Wuppertal HRB 36552
- webvalid, Co-reactive GmbH register announcements
- RWTH Aachen, three teams win Innovation Award, 2 February 2024
- EXIST, Co-reactive success story
- Holcim MAQER Ventures, accelerator programme
- Holcim, partnership with Paebbl and Goldbeck
- ATHENA grant office, 61 start-ups and SMEs secure EIC support, 17 February 2026
- European Innovation Council, 61 start-ups and SMEs secure EIC support
- European Commission, Carbon Border Adjustment Mechanism
Industry
ConstructionConstruction materials
AlsoClimate and environmentCarbon management
- Focus
- Concrete and cement
- Carbon utilisation
- Technologies
- Cement and concrete technology
- Chemical process engineering
- Keywords
- Supplementary cementitious materials
- Carbon dioxide utilisation
- Low-carbon concrete
- Fly ash replacement
- Steelmaking
- Clinker