Elonroad and the EIC Accelerator: Charging Port Vehicles on the Move

30 September 2026883 words5 min

Elonroad, based in Lund in southern Sweden, makes conductive charging rails set into the ground that power electric vehicles automatically, either while parked or while driving along a fixed route. After a public electric road demonstration in Lund, since dismantled, the company turned to ports, where heavy machinery follows predictable loops. It was selected in the EIC Accelerator's January 2023 cut-off for blended finance and received an EU grant of €2.50 million for a €3.59 million project that ran from August 2023 to July 2025, according to CORDIS.

The project is closed. Its final report states that Elonroad fully developed, certified and launched a static charging system as a commercial product with installations in Oslo and Malta, built a submerged dynamic rail tested in Sweden and Belgium, including a 200-metre track at Kalmar's yard where a reachstacker charged while moving, secured "a further contract for delivery to a major US port", and set up its first factory near its headquarters, according to the CORDIS reporting page. Its accounts show revenue of SEK 34.1 million in 2024, a net loss of SEK 23.1 million and equity of just SEK 0.5 million, according to hitta.se.

€2.50MEU grant
SEK 34.1MRevenue, 2024
SEK 0.5MEquity, end 2024
~SEK 90MNew share issue, May 2026

Company file

Legal entity
Elonroad AB, 556981-5862, Lund
CEO and co-founder
Karin Ebbinghaus
Founder
Dan Zethraeus
Products
Static charging stations; dynamic charging rail
Customers and sites named
Oslo, Malta, Kalmar, Long Beach (US)
Staff
34 in 2024
EIC funding
Blended finance; €2.50M grant

Where Elonroad Stands Now

In May 2026 Elonroad raised nearly SEK 90 million in a share issue directed to three new international investors, according to Rapidus. "It feels like hardware is starting to come back as an investment case," chief executive Karin Ebbinghaus told the paper, after "a long period of searching and courting". Its news page lists a Long Beach port contract, a collaboration with the Port of Oslo, and the dismantling of the Lund electric road after five years.

The record

From a street trial in Lund to port charging

Elonroad refocused from public roads to ports, launched a static charger and built a factory during its EIC project. Its equity almost ran out before a new share issue in May 2026.

  1. Jan 2023EIC Accelerator cut-offElonroadblended finance
  2. Aug 2023Project starts€2.50M EU grant
  3. Dec 2024Equity down to SEK 0.5MLoss of SEK 23.1M in 2024
  4. Jul 2025Project endsStatic charger on sale; Kalmar test track; US port contract
  5. May 2026Nearly SEK 90M raisedShare issue to three international investors

CORDIS, Elonroad, hitta.se and Rapidus.

"Our vision is to do things more efficiently, and to bring energy to where vehicles are."

Karin Ebbinghaus, CEO and co-founder, Elonroad, to CORDIS

The Technology: Power Where the Vehicle Is

Elonroad's rail is live only in segments directly under a passing vehicle, activated by an encrypted signal, so people can walk near it safely, the company explained to CORDIS. In ports, charging while moving means smaller batteries and no downtime. The final report says around 30% of the shipping industry's CO2 emissions come from ports, mostly from diesel equipment.

The accounts

Revenue and net result

Revenue doubled in 2023 and then stalled at about SEK 34M in 2024, while the net loss grew to SEK 23.1M.

hitta.se, from Elonroad AB's annual accounts. Values in SEK millions.

What the EIC Award Promised, and What the Record Shows

The award aimed to finish development, demonstrate static and dynamic charging in real operations and prepare industrial scale-up. The final report documents each step, with named sites. The commercial picture is weaker: revenue barely grew in 2024, losses deepened and short-term debt rose to SEK 65.9 million.

  1. Static chargerDeliveredCertified and sold.
  2. Dynamic charging demoDeliveredKalmar test track.
  3. ManufacturingDeliveredFactory near Lund.
  4. Financial strengthWeakEquity SEK 0.5M, 2024.

The Money

Elonroad lost SEK 53.5 million from 2022 to 2024, and staff grew from 24 to 34. Whether the EIC Fund invested under the blended finance award is not public.

The balance sheet

Equity against short-term debt

Equity fell from SEK 21.1M to SEK 0.5M in two years while short-term liabilities rose to SEK 65.9M.

hitta.se, from Elonroad AB's annual accounts. Values in SEK millions.

The project budget

Who paid for the €3.59M project

The EU covered 70% of the Elonroad project's cost.

CORDIS, project 190141800. Values in € millions.

What Cannot Be Checked

Questions for the EIC

Whether the EIC Fund invested, how Elonroad financed itself through 2025 with almost no equity, and what the Long Beach and Oslo contracts are worth are not public.

Why Europe Should Care

Electrifying ports cuts diesel emissions near cities, and Elonroad's approach reduces the need for big batteries. The company's own report credits EIC funding with bridging "the critical gap between early-stage innovation and market readiness". The hardware now works; the 2024 accounts show equity of just SEK 0.5 million, and a share issue followed in 2026.

What the award promised

Static and dynamic charging for port vehicles, demonstrated in operation and ready for industrial scale-up.

What the record shows

A commercial charger, a working test track, a factory and a US port order, plus equity of just SEK 0.5 million at the end of 2024 and a share issue in 2026.

The Verdict

Built, then refinanced

Elonroad delivered what the EIC funded. It then came close to running out of equity, until new investors stepped in in 2026.

Elonroad and the EIC have not been asked for comment for this article. It is based entirely on public records and published statements, linked throughout.

Industry

Mobility and transportElectric vehicle charging

Focus
  • Charging hardware
Technologies
  • Power electronics
Keywords
  • Port vehicles
  • Dynamic charging
  • Electric roads
  • Heavy machinery
  • Conductive charging