Kraftblock and the EIC Accelerator: Storing Industrial Heat
PepsiCo's crisp factory in Broek op Langedijk, in the Netherlands, fries its snacks with heat from a 25 MW gas boiler. Replacing it with wind and solar power means storing energy for when the sun and wind are absent, and storing it as heat. Kraftblock, a company from Sulzbach in Saarland, stores electricity or waste heat as heat in containers filled with a material made from upcycled industrial by-products, and releases it when a plant needs it. The EIC-funded version was designed for temperatures up to 1,300°C.
The EIC selection list used the former name NEBUMA GmbH; the company now trades as Kraftblock GmbH. Investor Koolen Industries already described it under that name in September 2020. The European Innovation Council granted €1,788,062 towards a €2.55 million project to build a container-sized storage module. Shell Ventures then led a €20 million round. Tata Steel confirms operation in India. Kraftblock also reports an operating mobile-heat system with Buhck in Germany. The reviewed sources do not settle commissioning of the larger PepsiCo project in the Netherlands.
Company file
- Legal entity
- Kraftblock GmbH (formerly NEBUMA GmbH), Saarbrücken HRB 101387
- Headquarters
- Sulzbach, Saarland, Germany
- Co-founders
- Martin Schichtel (CEO), Susanne König (chief external affairs officer)
- Product
- Containerised high-temperature thermal energy storage
- Projects
- Tata Steel (India), PepsiCo with Eneco (Netherlands)
- Series B investors
- Shell Ventures (lead), Finindus, Moore Strategic Ventures, A&G, TechEnergy Ventures, Future Industry Ventures
- EIC project
- KRAFTBLOCK, 1 Mar 2022 to 31 Dec 2024, closed
- EIC funding
- Grant only
Where Kraftblock Stands Today
Tata Steel's 27 February 2026 release describes nearly a year of reliable operation at Jamshedpur's Sinter Plant 3, recovering waste heat to warm process water. It attributes annual CO2 reductions of 22,000 tonnes to the system, without publishing the calculation here. Trade coverage reports 20 MWh capacity and a May 2025 start; that date does not align precisely with the operator's approximate one-year description, so an exact start date is not established here.
The Dutch project has differing timing descriptions. Kraftblock's Volt page lists 70 MWh for phase one, 800 degrees C storage and an operation date of early 2025, while much of its text remains prospective. Eneco's construction update records resumption of work on 17 February 2025, following a site closure. A 2026 thermal-storage handbook hosted by DLR describes commissioning with commercial operation in 2026. These pages do not establish a completed commissioning date or sustained output as of this review on 2 November 2026. Savings figures remain design/forecast claims, not measured results established here.
The projects
Reported Tata capacity and PepsiCo design capacities
Selected projects, not a complete deployment inventory. Capacities in MWh; PepsiCo second phase is total site capacity, not an additional 150 MWh. Commissioning unresolved at review.
Canary Media; Modern Power Systems; Kraftblock project page for PepsiCo (Volt).
The Technology: Heat Kept in Slag
A Kraftblock unit heats air, either with an electric heater running on cheap renewable power or with a factory's waste heat, and blows it through a container of heat-storing material. When heat is needed, air is blown back through to recover it. The storage material is made from upcycled industrial by-products, according to the EIC award, and the CORDIS summary describes storage at up to 1,300°C with conversion back into heat and electricity. For PepsiCo the system is designed to run at 800°C.
"...the resilience and solid business of Kraftblock and proves our great potential."
Susanne König, then CFO, on the Series B, via TechEnergy VenturesWhat the EIC Project Promised, and What CORDIS Shows
The EIC project
EU contribution: 70% of a €2.55M project
The KRAFTBLOCK project ran from March 2022 to December 2024.
CORDIS project 190167786. Values in € millions.
The project ran from March 2022 to December 2024. Its beneficiary summary reports container designs and simulations, material-temperature tests, and 4,700 accelerated pellet-test cycles without observed degradation. It distinguishes capacities above 35 MWh for a 20-foot large-scale module from above 24 MWh for a separately insulated module. Those design figures are not evidence that a complete prototype delivered 35 MWh in service. The report describes charging at Dillinger/Saarstahl, but says only two of three container-design phases were finished and refers to planned patent filings. It does not establish completion of every objective.
- A container module at 1,300°CDeliveredBeneficiary-reported design and material results; full-system operation at every claimed temperature/capacity is not established by the summary.
- Durable storage materialDeliveredNo degradation observed in 4,700 accelerated pellet-test cycles, per the beneficiary; not 4,700 cycles of a complete industrial plant or proof of 15,000-cycle life.
- Industrial deploymentPartialTata Steel confirms operation; Kraftblock also identifies a German Buhck system. PepsiCo commissioning remains unresolved in the reviewed sources.
- Power generation from stored heatNot shownThe Tata Steel and PepsiCo sources reviewed on 2 November 2026 concern heat supply; they do not establish measured electricity generation.
What Has Happened Since the Award
The record
From lab material to a steel mill in India
Tata Steel confirms industrial operation; Kraftblock also reports a German Buhck system. PepsiCo commissioning is unresolved in the sources reviewed on 2 November 2026.
- By Sep 2020NEBUMA becomes KraftblockInvestor announcement already uses Kraftblock and identifies former name NEBUMA
- Jun 2021EIC Accelerator cut-offModular 1,300°C heat storage made from industrial by-products
- Mar 2022EIC project startsContainer storage and pilot charging at a Saarland steel mill€1.79M grant
- May 2023PepsiCo project announcedHeat storage with Eneco for a crisp plant at Broek op Langedijk
- Aug 2023Series BLed by Shell Ventures€20M
- Dec 2024EIC project closesBeneficiary reports 4,700 pellet-test cycles and module designs; not proof of complete-plant endurance or measured capacity
- 2025Tata Steel system runningTrade coverage reports 20 MWh capacity; exact start differs from operator description
- Feb 2026Tata Steel operation updateOperator describes approaching a year of reliable pilot operation
German company register via companyhouse.de, CORDIS, TechEnergy Ventures, Eneco, Kraftblock, Canary Media and Tata Steel.
The Money
The money
Shell's round dwarfed the EIC grant
Disclosed funding in millions of euros.
CORDIS; TechEnergy Ventures; EU-Startups.
The Series B, led by Shell Ventures with Finindus, Moore Strategic Ventures, A&G Energy Transition Tech Fund, TechEnergy Ventures and Future Industry Ventures, was reported in August 2023 by TechEnergy Ventures and EU-Startups. It was to fund a larger team and more production capacity. The EIC award was grant-only, with no equity.
What cannot be checked
Original recent accounts were not retrieved in this review, so current liquidity, revenue and system costs remain unverified here. Searches of company press pages and funding announcements on 2 November 2026 did not establish a later financing round. That does not show that no funding occurred or that project delivery is constrained by cash. Eneco says it will own and operate the PepsiCo system; financing responsibility cannot be inferred from Kraftblock's funding announcements alone.
Why Europe Should Care
Heat storage is one of the few ways to let a factory run its high-temperature processes on intermittent renewable power, and Kraftblock builds it partly from European heavy industry's own waste. The company history also identifies the German Buhck mobile heat system as operating since April 2023, so the Indian installation should not be described as its first or only industrial deployment.
What the project promised
Scalable, modular, cost-efficient storage at up to 1,300°C that returns heat and power, made from upcycled by-products.
What the record shows
A tested container module, a working 20 MWh system in India and a €20M round, with PepsiCo commissioning unresolved in the reviewed sources.
The Verdict
Operator-confirmed progress, commissioning questions
The project summary supports reported engineering progress, and Tata Steel confirms a working industrial application. Material tests and module designs do not independently prove completion of all engineering targets or long-term plant performance. For PepsiCo, the reviewed construction, supplier and handbook sources leave commissioning and sustained output unresolved; this is not proof that the system failed or that it is not operating.
Kraftblock has not been asked for comment for this article. It is based entirely on public records, company statements and EU project data, linked throughout.
Industry
EnergyEnergy storage
- Focus
- Thermal energy storage
- Technologies
- Waste heat recovery
- Power-to-heat
- Keywords
- Industrial heat
- Industrial decarbonisation
- Steelmaking
- Food processing