Promethean Particles and the EIC Accelerator: Scaling Up MOFs
Promethean Particles, founded in 2007 on research by Professor Ed Lester at the University of Nottingham, manufactures metal-organic frameworks (MOFs), porous crystals with enormous internal surface areas that can trap gases such as CO2, using continuous-flow reactors that it says make them cheaper and more consistent than batch production. It was selected in the EIC Accelerator's June 2023 cut-off with a grant-only award for REMBRANDT, "Rapidly Accelerating MOF-based Sorbents as a Novel Decarbonisation Technology", which its website lists as a 2024 to 2026 project, according to Promethean Particles. The company says it won a £2.1 million grant through the EIC Accelerator, with the funding coming from Innovate UK, according to Promethean Particles. UKRI's Gateway to Research lists REMBRANDT as a Horizon Europe Guarantee grant of £2,101,136 running from 1 April 2024 to 30 September 2026, according to UKRI. We did not find a CORDIS record, and no project results have been published.
In November 2025 Promethean fulfilled its largest-ever order, manufacturing and shipping four tonnes of MOFs to a customer in continental Europe for "an energy-efficient gas storage application", according to Promethean Particles. In July 2026 Ahbstra launched ARK, an atmospheric water harvesting system producing up to 500 litres a day using Promethean's ProMOF 1300, according to Promethean Particles. In February 2026 it demonstrated MOF carbon capture to the Duke of Edinburgh at an Institute of Physics showcase, according to Promethean Particles. Its earlier MONET project tested a prototype MOF carbon capture unit on flue gas at Drax's CCUS incubation site under a UK government competition, according to the Department for Energy Security and Net Zero. Sources reviewed on 7 November 2026 do not show a named commercial carbon capture customer.
Company file
- Legal entity
- Promethean Particles Ltd, company 06427290
- CEO
- James Stephenson
- Origin
- University of Nottingham, Professor Ed Lester
- Product
- ProMOF metal-organic frameworks
- Investors
- Mercia Ventures, Aramco Ventures, Midlands Engine Investment Fund, University of Nottingham
- Applications
- Carbon capture, gas storage, water harvesting, biogas
- EIC funding
- £2.1M grant, paid via Horizon Europe Guarantee
Where Promethean Particles Stands Now
Promethean raised £8 million in August 2024 in a Series A co-led by Mercia Ventures and Aramco Ventures, the venture arm of the Saudi oil company, according to Promethean Particles. Its accounts show average staff rising from 11 in 2023 to 22 in 2025, cash of £5.93 million at the end of 2025, and losses of £1.06 million in 2024 and £0.44 million in 2025, according to filings at Companies House. It appointed its first chief financial officer in October 2025, and founder Ed Lester left the board in February 2026.
The record
From university reactor to tonne-scale MOF orders
Promethean Particles raised £8 million in 2024, fulfilled its largest order of four tonnes in 2025, and supplied MOFs for a water-from-air system launched in 2026, while its EIC-backed REMBRANDT project ran.
- 2007Company foundedUniversity of Nottingham research
- 2016Genesis Park siteContinuous MOF manufacturing plant
- Jun 2023EIC Accelerator cut-offREMBRANDT£2.1M grant
- Aug 2024£8M Series AMercia Ventures, Aramco Ventures
- Nov 2025Four-tonne MOF orderLargest ever, for gas storage
- Feb 2026Founder leaves boardCFO joins board
- Jul 2026Ahbstra ARK launchedWater harvesting with ProMOF 1300
Promethean Particles and Companies House.
"There is no doubt that this four-tonne order represents the accomplishment of a major milestone in our MOF manufacturing."
James Stephenson, CEO, November 2025The Technology: Molecular Sponges at Tonne Scale
MOFs are built from metal ions linked by organic molecules into lattices full of tiny pores, which can be tuned to capture specific molecules. Industrial adoption was held back by a lack of scalable manufacturing and high costs, the company says. Its patented continuous flow hydrothermal synthesis makes identical MOFs at different scales, in what it describes as the world's largest continuous MOF plant. REMBRANDT aimed to speed up the use of MOF sorbents for capturing CO2, which the company presents as a lower-energy route for industry.
The growth
Average employees
Promethean Particles doubled its workforce between 2023 and 2025.
Companies House, Promethean Particles Ltd accounts. Average employees.
What the EIC Award Promised, and What the Record Shows
REMBRANDT's goal, as its name says, was decarbonisation with MOF sorbents. What the record shows is a company that has scaled its manufacturing and won its biggest orders in gas storage and water harvesting. Whether REMBRANDT delivered its carbon capture milestones cannot be checked: the UKRI record lists the award and its aims, but no results.
- Industrial MOF supplyDeliveredFour-tonne order.
- Commercial products using MOFsDeliveredAhbstra ARK, 2026.
- Carbon capture deploymentUnverifiedNo customer named.
- EIC project reportingUnverifiedNo results published.
The Money
Before the Series A, Promethean's cash had fallen to £184,640 at the end of 2023. The 2024 round restored its balance sheet. UKRI lists the REMBRANDT award at £2,101,136 under the Horizon Europe Guarantee, the UK scheme that funds British EIC winners. How much of it has been paid out is not shown.
The accounts
Cash and net assets at year end
Cash fell to £184,640 at the end of 2023 before the Series A lifted it to £6.48 million. The company lost £1.06 million in 2024 and £0.44 million in 2025.
Companies House, Promethean Particles Ltd accounts. Values in £ millions.
What Cannot Be Checked
Questions for the EIC
How much of the £2.1 million REMBRANDT grant was paid out, what the project achieved on carbon capture, and what the company's revenue is are not public.
Why Europe Should Care
The 2025 Nobel Prize in Chemistry went to the scientists who developed MOFs. A supplier that can make them by the tonne addresses the bottleneck the company itself names: until recently MOFs were produced in grams or kilograms. Promethean is building that capacity in the UK, with backing that includes Saudi Aramco's venture arm. Sources we reviewed on 7 November 2026 show no announced carbon capture orders.
What the award promised
Faster adoption of MOF-based sorbents for decarbonisation.
What the record shows
Tonne-scale MOF supply for gas storage and water harvesting, and no public carbon capture customer.
The Verdict
Growing, in other markets
Promethean has scaled up since its EIC selection. Its carbon capture business, the focus of the award, is not yet visible.
Promethean Particles and the EIC have not been asked for comment for this article. It is based entirely on public records and published statements, linked throughout.
Sources
- Promethean Particles, company history
- Promethean Particles, four-tonne MOF order, November 2025
- Promethean Particles, Ahbstra ARK, July 2026
- Promethean Particles, £8M Series A, August 2024
- Promethean Particles, Duke of Edinburgh showcase, February 2026
- Companies House, Promethean Particles Ltd filings
- UKRI Gateway to Research, REMBRANDT grant 10111050
- Promethean Particles, Project REMBRANDT team members, November 2024
- DESNZ, CCUS Innovation 2.0: MONET project
Industry
Materials and chemicalsAdvanced materials
- Focus
- Porous materials
- Technologies
- Flow chemistry
- Keywords
- Carbon capture
- Gas storage
- Sorbents
- Water harvesting
- Continuous flow synthesis