RheEnergise, an EIC Accelerator Winner, Pumps Heavy Fluid Uphill
Conventional pumped hydro needs around 500 metres of height and, in the words of RheEnergise's own report to the UK government, "decade-long timescales" to build. RheEnergise, a London company incorporated in 2019, keeps the principle and changes the liquid: its closed-loop system pumps a mineral suspension about 2.5 times as dense as water between two buried reservoirs, so that, by the company's account, a hill of 75 to 300 metres can do the same work.
The EIC Accelerator selected RheEnergise's project LDES-HDHydro at its March 2025 cut-off for a grant-only award, and CORDIS records an EU contribution of €2,499,999 for October 2025 to September 2027. The grant is not paying for the first plant. That was built near Plymouth with UK government money, and the government has published the company's final project report on it, which is considerably more detailed, and more candid, than the company's press releases.
Company file
- Legal entity
- RheEnergise Limited, company 11927250, England and Wales
- Incorporated
- 5 April 2019
- Registered office
- Collective Auction Rooms, 5-7 Buck Street, London
- Leadership
- Stephen Crosher (chief executive), Tamás Bertényi (co-founder, chief technology officer), Graham Cook (chief financial officer)
- Staff
- Average of 11 employees in 2025, 12 in 2024 and 2023, per the filed accounts
- Known investors
- Low Carbon Innovation Fund; crowdfunding on Crowdcube, FrontFundr and Republic
- Demonstrator
- 500 kW at Sibelco's Cornwood kaolin mine near Plymouth, Devon
- EIC project
- LDES-HDHydro, agreement 101248115, signed 9 October 2025, running to 30 September 2027
A heavier fluid instead of a higher hill
The energy a pumped hydro plant stores is the weight of its liquid times the height it is lifted. Raising the density by a factor of 2.5 lets either the height or the reservoir volume shrink by the same factor. IEEE Spectrum describes the fluid as a proprietary mineral suspension of about 80% solid particles by mass, which thins when pumped and thickens at rest; the company's report to the UK government names barite powder as one of its ingredients. Both reservoirs are buried and the loop is sealed, which the report says needs 20% of the water volume of conventional pumped hydro and a smaller footprint.
The claims for commercial plants are the company's. The LoDES report, which the Department for Energy Security and Net Zero published and which RheEnergise wrote in the first person, says plants would be 60% smaller by volume than water-based ones, last more than 60 years and reach 80% round-trip efficiency, and that a typical project would be 40 MW with ten hours of storage. Its cost comparison, built on a model by consultancy Mott MacDonald, puts high-density hydro below lithium-ion batteries beyond about four hours of storage. None of these figures has been demonstrated at commercial scale, because no commercial plant exists.
The minimum height is described differently by different sources: tech.eu reported 100 metres or less in July 2025, the report gives 75 to 300 metres, and IEEE Spectrum puts the demonstrator's upper reservoir at 80 metres.
"Larger scale deployment will require substantial civil works, permit requirements, and engineering coordination."
George Aggidis, professor emeritus of energy engineering at Lancaster University, quoted by IEEE Spectrum, 25 February 2026The Devon plant: what the LoDES report says
The UK government's Longer Duration Energy Storage (LoDES) programme awarded RheEnergise just over £8 million in September 2022 for a 500 kW demonstrator with four hours of storage, according to the report. The first site, at the Hemerdon mine, fell through in November 2023 over the mine's operating permits; a lease at Sibelco's china clay mine near Plymouth followed in April 2024, and surveys, design, planning and the grid application had to be repeated. The construction programme, compressed from 16 to 11 months to fit the funding rules, was extended in December 2023 to May 2025 and then to November 2025.
The record
Three and a half years from UK award to full power in Devon
The demonstrator moved site once and was extended twice before it ran at 500 kW; the EIC grant began while commissioning was still under way.
- Apr 2019Company incorporatedRheEnergise Limited registered in England and Wales
- Sep 2022UK demonstrator awardJust over £8 million from the government's LoDES programme for a 500 kW, four-hour demonstrator£8.2M
- Nov 2023First site falls throughTalks for the Hemerdon mine site halt over the mine's operating permits
- Apr 2024New siteLease signed at Sibelco's china clay mine near Plymouth; surveys, design and permits repeated
- Mar 2025EIC Accelerator cut-offLDES-HDHydro selected for a grant-only award
- Oct 2025Grant signed, scope cutCORDIS project starts; the demonstrator's fluid volume is cut from 1,420 to 540 cubic metres€2.5M
- Dec 2025Heavy-fluid commissioningEnds in sustained operation at the design output of 500 kW, per the final report
- Jan 2026Full power announcedThe company says the Cornwood plant runs at full power at its predicted output
- Oct 2026Italy agreementMemorandum of understanding with developer Ikigai Energy, per the company
- Sep 2027LDES-HDHydro endsScheduled end of the EIC project, which is to design a 5 MW turbineScheduled
Companies House; DESNZ LoDES Phase 2 final report, February 2026; CORDIS; RheEnergise, 27 January 2026 and news page.
The report lists the problems on the way. Both reservoirs were cut in size by 50% to save money. The first batch of fluid did not match the design because one additive differed chemically from the tested version, which the report says its manufacturer knew about but had not flagged. A valve failure during the first operation of the fluid system required a clean-up of the powerhouse. The company wrote that its designer and owner's engineer, chosen for experience with small conventional hydro, "lacked the breadth needed" for the project, contributing to "late identification of defects".
The largest change came in October 2025. With the government programme closing, RheEnergise cut the fluid volume from 1,420 to 540 cubic metres, which the report says reduces running time at full power to about 15 minutes. It calls this a minimum viable product and "a compromise to the original scope". Production reached 32% of the design rate, slowed by damp barite powder, and 465 cubic metres were mixed to specification in just over five weeks. The report states an intention to produce the rest of the fluid later in 2026; whether that has happened has not been published.
The scope change
The plant was built for four hours and filled for fifteen minutes
Cubic metres of high-density fluid: the volume first planned, the reduced volume agreed in October 2025, and what was mixed to specification before project closure. The report puts the reduced volume at about 15 minutes of running at full power.
DESNZ, LoDES Phase 2 final project report, February 2026.
The test results are positive within those limits. Over more than 100 pump and turbine operations, the turbine reached a peak efficiency of 89.6% with water and 84.8% with the dense fluid, and the measured efficiencies of each stage came within three percentage points of the computer models. The whole plant returned 59% of the energy put in, against a modelled 56%, before parasitic losses that the report says have not yet been measured. The company expects larger machines to close the gap to its 80% target; that is a projection, not a result.
The test results
The measurements beat the model, and the round trip reached 59%
Efficiency of the 500 kW demonstrator as modelled and as measured on site. The round-trip figure excludes parasitic losses; the company's target for commercial plants is 80%.
DESNZ, LoDES Phase 2 final project report, RheEnergise High Density Hydro, February 2026, Table 2.
The dates of full power differ slightly between sources. The report says commissioning with the dense fluid took place in December 2025 and ended in sustained operation at 500 kW. The company's press release of 27 January 2026 and ESS News reported full power that month, with the plant supplying the Sibelco mine at times of high demand.
What the company said
The plant performs "exactly as predicted", and "we have proven and critically de-risked our high-density hydro technology", chief executive Stephen Crosher told ESS News; the company says commercial-scale projects in the UK and abroad will follow.
What the record shows
A 500 kW plant that reached full power, with turbine results close to the models, but built with half-size reservoirs, filled with about 15 minutes of fluid at full power, at 59% round-trip efficiency before parasitic losses, and over budget.
Who paid, and how much is left
The UK figure is reported in different ways. ESS News gave £8.25 million; the report says the award rose from £8.2 million to £9.8 million, then fell by £64,500 when the fluid volume was cut, to £9,806,109. Total project spend reached £10.2 million, more than the funding, the report says, and it gives inflation, the change of site, the extended programme and unbudgeted extra work as the reasons.
The UK money
The demonstrator cost more than the state paid for it
The original UK award, the final award after increases and a small reduction, and what the project actually spent.
DESNZ, LoDES Phase 2 final project report, February 2026. Values in £ millions.
The equity rounds that are public are small. Renewable Energy Magazine reported in February 2024 that the Low Carbon Innovation Fund put in £335,000 as the cornerstone of a £720,000 round, alongside a Crowdcube campaign. The company's news page announced a Canadian crowdfunding campaign on FrontFundr in May 2025 and a North American one on Republic in September 2025. A Form D filed with the US Securities and Exchange Commission on 7 April 2026 reports $158,090 sold to 63 investors in a $2,999,996 offering. The Republic total could not be read directly, and no amount for the FrontFundr campaign could be verified.
The Companies House filing history shows share allotments in January, March and December 2025 and in June and September 2026, and a charge created on 22 July 2026. The unaudited small-company accounts, which do not include an income statement, show net assets falling from £1,182,952 at the end of 2024 to £575,126 at the end of 2025, with £854,381 in the bank. They also record a convertible loan of £676,546 including interest, at 8%, secured by a debenture over the company's assets and repayable on 20 June 2026 unless converted; after the year end, the directors wrote, they began negotiating a six-month extension. How that loan was settled is not public. The directors also chose not to capitalise any development costs, because "the probability of future economic benefit is currently uncertain".
The balance sheet
Net assets halved in 2025
Net assets at 31 December, from the unaudited small-company accounts. No income statement is filed, so the loss for each year is not public.
Companies House, RheEnergise Limited accounts for 2024 and 2025. Values in £ thousands.
The report said in February 2026 that the company was pursuing more crowdfunding in the short term and "series A investment within the next six months". Searches of news coverage, the company's news page and the SEC's EDGAR database on 28 October 2026 found no announced Series A round.
What the EIC grant is for
According to CORDIS, LDES-HDHydro is to optimise and test the company's turbine for the dense fluid, finalise a manufacturing and scale-up strategy for a 5 MW prototype and take the technology to readiness level 8. The LoDES report describes the grant as funding the design of a 5 MW commercial-scale turbine, after which the company aims to build a 10 MW, six-hour first commercial project. Commercial plants are to use two or four 5 MW turbines, with the first fully commercial system targeted for the end of 2028, IEEE Spectrum reported; the January 2026 press release said within three years.
A year into the grant, CORDIS lists no deliverables or reports, which is normal at this stage. CORDIS and the LoDES report also disagree on patents: CORDIS cites 20 patents in 11 families, while the LoDES report counts 17 applications, of which 3 were granted.
- Optimise and test the turbine for dense fluidRunningThe 500 kW demonstrator turbine reached 84.8% peak efficiency with the fluid, per the LoDES report; no output of the EIC project is published yet.
- Design a 5 MW turbine and scale-up strategyNot yet reportedIEEE Spectrum reports work with turbine manufacturers; no 5 MW design or test result is published by October 2026.
- Reach readiness level 8TRL 6 to 7The report claims TRL 7 for the demonstrator, which ran on a reduced fluid volume.
- First commercial projectPipeline onlyCandidate sites in Poland, Scotland and Italy, per the report; none announced as financed.
Customers, sites and the European case
The report names mines and quarries, data centres, constrained grid locations and vertically integrated utilities as first customers, and says the company has signed three memoranda of understanding with developers on three continents and holds a pipeline it values at $1.75 billion of project capital across 35 opportunities. The candidate first projects it lists are a 10 MW, six-hour plant in south-east Poland at the environmental permit stage, two 10 MW plants on Scottish estates and sites in Italy. In October 2026 the company announced a memorandum with developer Ikigai Energy to assess sites starting in Italy, also reported by Energy-Storage.news. A memorandum is not a contract, and none of these projects has announced financing.
The project sits within EU storage policy. The European Commission's recommendation on energy storage of March 2023 asks member states to identify flexibility needs and ease permits for storage, and CORDIS tags the project 100% to climate action. The CORDIS summary sets the system against lithium-ion batteries, which it describes as covering only two to four hours and depending on constrained supply chains. The UK is an associated country in Horizon Europe, per Innovate UK Business Connect, and the UK government targets 4 to 6 GW of long-duration storage by 2030, per ESS News.
Verdict
RheEnergise has run a pumped hydro turbine at full power on a fluid 2.5 times as heavy as water, with results close to its models. The company's own report to the government also shows a plant that changed site, halved its reservoirs, ran over budget and was filled with about 15 minutes of fluid at full power instead of four hours, at 59% round-trip efficiency. The EIC grant pays for the next step, a 5 MW turbine design, while the company's net assets halved in 2025 and the Series A it planned has not been announced.
The reporting is based on publicly available sources, listed below.
Sources
- CORDIS, LDES-HDHydro project fact sheet
- Department for Energy Security and Net Zero, LoDES Phase 2 final project report, RheEnergise High Density Hydro, February 2026
- Companies House, RheEnergise Limited company overview
- Companies House, RheEnergise Limited filing history and accounts for 2024 and 2025
- RheEnergise, Full power achieved, 27 January 2026
- RheEnergise, news page
- IEEE Spectrum, This high-density hydro storage system ditches the water, 25 February 2026
- ESS News, RheEnergise commissions first high density hydro LDES in UK, 27 January 2026
- tech.eu, RheEnergise secures €2.5M to accelerate green energy storage tech, 4 July 2025
- Renewable Energy Magazine, RheEnergise secures equity investment from Low Carbon Innovation Fund, 12 February 2024
- US Securities and Exchange Commission, RheEnergise Ltd Form D, filed 7 April 2026
- Energy-Storage.news, Developer Ikigai partners with high-density hydro LDES tech firm RheEnergise for Italy projects
- European Commission, Recommendations on how to exploit the potential of energy storage, 14 March 2023
- Innovate UK Business Connect, Horizon Europe eligibility essentials
Industry
EnergyEnergy storage
- Focus
- Mechanical storage
- Technologies
- Turbomachinery
- Fluid dynamics
- Hydraulic engineering
- Keywords
- Long-duration storage
- Pumped hydro
- Grid storage
- Mining
- Data centres